2007-08-03

【2007/8/2】The meeting with Hamzeh and Kamal


① Web workshop (the responsibility is Mr. Kamal Jabr)
■ The date: 2007/ Aug/ 11, 12, 13, 14
■ Preparation:
1) The preliminary inspection: 2007/ Aug/ 9 at 13:00 at DTC
2) The transportation: From EDC to DTC at 8:30 (Mr. Najime have arranged)
3) The contract of internet server: Kamal will make contract with company (at the beginning of August for 1 year)
4) The participants list (Kamal will prepare)
5) Information sheet (Kamal will prepare)

② Students Learning Community (SLC)
■ The date: 2007/ Aug/ 6, 7, 8, 9
■ Preparation
1) Making program
2) Prepare stuffs and equipments needed for the SLC
3) Fee for drink and snacks (20 dollars)
4) Supporting staffs
・ SLC for science ( Taka, Kamal, Loai, Nasma, Amar, Najaha)
・ SLC for health education ( Jumpei, Hamzeh, Ahamad, Jamar, Hiba, Riem)
・ SLC for T-shirt making (Iburahim, Marwan, Nori, Miki, Mako )
5) Introduce Thinking Tool (for worksheet)

③ The conference of educational technology in Japan
・ Interview
・ Data (pictures etc) for presentation

④ The presentation on 5th
■ The date: 2007/ Aug/ 5
■ The participants: school supervisors, head teachers, teachers
■ Preparation
1) Comment sheet (Kansai Univ staff will prepare)
2) Computer, Speaker, Projector, and Screen ( Already prepared in EDC)
3) Gathering Portfolio
4) Rubric in Arabic
■ Announcement
・ Monitoring in November
・ Introduce BLOG as learning activity
・ Make appointment of the interview
■ The important memo
1) When do we give Certification to teachers?
→Certification will be given to those who complete portfolio and play an active part in teachers’ learning community (TLC).
2) When do we implement facilitator training?
→Hamzeh and Kamal will prepare with the teachers who are excellent in the project as facilitator.
3) When do we have workshop of LCA by teachers?
→Hamzeh and Kamal will prepare with the teachers who are excellent in the project as facilitator.
4) When and how do we evaluate teachers’ portfolio?
→We will discuss with Mr. Annmouri if it is possible to form evaluation committee for next stage with supervisors?

No comments: